For the past many months a Worship Space ImProvement Team (WSIP) team at St.
Paul has been
moving our worship space renovation project forward. I'm very happy
to say our project is complete.
The 2008 renovation project included:
- Reworking the front step area to give us additional space
up front.
- Replacing old carpet with a combination
of wood flooring and carpet as shown in the concept below.
- Replacing old pews with a combination of
new pews and pew chairs from New Holland Church Furniture.
- Painting walls.
- Construction of portable kneeling rails
from old communion rail.
- Carpeting balcony and move choir
area pews to balcony.
Following are preliminary pictures showing
the results of the renovation effort.
|
|

Sanctuary ready for services on 6/22/08
|
|

Looking out to the congreation
|
|

The Renovated Balcony
|
|

Moveable Kneeler Constructed from 1952 Communion Rail by Sonny
|
|
Schedule and Status of St. Paul Sanctuary Renovation Efforts
| Date |
Task |
Status |
|
May 18
|
Last Sunday in sanctuary before renovation starts. |
|
|
May 19-30
|
Sanbower
Builders carpentry work starts and completes. |
Done! |
|
May 20 |
Sanctuary pews removed and dismantled by St. Paul Team. |
Done! |
|
May 27 |
Balcony pews removed from balcony by St. Paul Team. |
Done! |
|
May 27-June 8
|
Painting of Sanctuary by Dunn
Decorating |
Done! |
|
May 31
|
Deadline for members to have their pews
removed. |
Done! |
|
June 2-15
|
Stroup
Flooring wood flooring and carpet work to
start and complete. |
Done! |
|
June 17-19
|
New
Holland Church Furniture to deliver and install new pews and pew
chairs. |
Done! |
|
June 19 7:00PM
|
Clean-up Sanctuary and move in.
Dust everything
Polish the wood work
Mount railings and balcony pews
Move back in.
|
Done! |
|
June 22
|
First Sunday in new space! |
Done! |
|
|
Some scenes from the renovation effort.
|
|

Our proud New Holland Installation Team as they complete their final efforts!
|
|

Completed floors before pew installation
|
|
 
Carpeted Balcony ready to move in!
|
|
Thanks to all those that helped make this project so successful, on time and
within budget!
Carpentry work by Sanbower Builders.
Walls freshly painted courtesy of Bruce Dunn of Dunn
Decorating.
New flooring from Stroup
Flooring America.
Pews and Chairs by New
Holland Church Furniture
Moveable kneeler by Sonny
Thanks to the WSIP team for their visioning and hard work pulling this effort
together.
Thanks to the St. Paul members who provided the funds to make this a reality.
|
|
For additional information contact:
St. Paul
Lutheran Church
|